[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130448":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130448,794,2,"多选题","抓斗式挖泥船作业时应根据（ ）确定下斗间距和前移量。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","土质",true,{"key":16,"text":17,"correct":18},"B","挖宽",false,{"key":20,"text":21,"correct":18},"C","挖深",{"key":23,"text":24,"correct":14},"D","泥层厚度",{"key":26,"text":27,"correct":18},"E","斗容","AD","2020版教材页码P198-P201 挖泥作业时，应根据土质和泥层厚度确定下斗的间距和前移量。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]