[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130446":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130446,794,2,"多选题","链斗挖泥船应在（ ）分段施工。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","挖槽边线为折线时",true,{"key":16,"text":17,"correct":18},"B","挖槽内泥层厚度相差较大时",false,{"key":20,"text":21,"correct":14},"C","挖槽规格不一时",{"key":23,"text":24,"correct":18},"D","挖槽内流速较大时",{"key":26,"text":27,"correct":14},"E","能避免或降低航行施工干扰时","ACE","2020版教材页码P188-P193 分段施工： （1）挖槽长度大于挖泥船水上管线的有效长度时，应根据挖泥船和水上管线所能开挖的长度进行分段。 （2）挖槽边线为折线时，应按边线拐点进行分段。 （3）挖槽规格或工期要求不同时，应按挖槽规格变化和工期要求进行分段。 （4）选择的施工方法和工艺参数因施工区土质变化相差较大时，应按土质进行分段。 （5）分段施工能避免或降低航行及其他施工干扰时，应根据商定的避让办法进行分段。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]