[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130445":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130445,794,2,"多选题","绞吸式挖泥船在（ ）情况下分层施工。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工干扰",false,{"key":16,"text":17,"correct":18},"B","挖泥船最大挖深在高潮挖不到设计深度时",true,{"key":20,"text":21,"correct":18},"C","当地水深在低潮不足挖泥船装载吃水时",{"key":23,"text":24,"correct":18},"D","当工程需要分期达到设计深度时",{"key":26,"text":27,"correct":18},"E","泥层厚度较厚时","BCDE","2020版教材页码P180-P188 绞吸式挖泥船分层施工： （ 1 ）施工区泥层厚度较厚时应分层施工。 （ 2 ）当挖泥船最大挖深在高潮挖不到设计深度，或当地水深在低潮不足挖泥船装载吃水时，应利用潮水涨落进行分层施工，高潮挖上层，低潮挖下层。 （ 3 ）当工程需要分期达到设计深度时，应按分期的深度要求进行分层。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]