[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130437":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130437,794,2,"多选题","排水盲沟开挖应（ ），其断面尺寸应满足设计要求。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","分片分段",true,{"key":16,"text":17,"correct":18},"B","自上而下",false,{"key":20,"text":21,"correct":18},"C","分条分段",{"key":23,"text":24,"correct":14},"D","自下而上",{"key":26,"text":27,"correct":18},"E","分层分段","AD","2020版教材页码P170-P176 排水盲沟施工应符合下列规定: （1）盲沟开挖应分片分段、自下而上进行，其断面尺寸应满足设计要求。 （2）盲沟开挖经验槽合格后应及时铺设土工织物、填充料等倒滤层。 （3）盲沟内土工织物与沟壁应紧密贴实，不得形成地下过流通道;铺设在同一直线段基槽内的土工织物宜采用整幅布料，不得拼接。 （4）盲沟填充骨料的粒径、级配、铺设厚度应满足设计要求，骨料回填宜采用人工分段自下而上、从一端往另一端铺设施工。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]