[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130432":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130432,794,2,"多选题","砂枕坝体施工前，应根据（ ）等绘制坝体断面砂枕布置图。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","河床地形",true,{"key":16,"text":17,"correct":18},"B","冲刷情况",false,{"key":20,"text":21,"correct":14},"C","坝体设计高程",{"key":23,"text":24,"correct":14},"D","坝体设计坡比",{"key":26,"text":27,"correct":18},"E","地基承载力","ACD","2020版教材页码P165-P169 砂枕坝体施工前，应根据河床地形、坝体设计高程及坡比，绘制坝体断面砂枕布置图。施工中应考虑施工顺序和施工荷载对坝稳定的影响，以及因地基沉降和充填袋内砂体密实而引起的顶部高程降低。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]