[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130426":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130426,794,2,"多选题","斜坡堤在安装护面块体前，应对堤身以下项目进行检查：（ ），不符合要求时，应进行修整。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","块石垫层厚度",true,{"key":16,"text":17,"correct":14},"B","块石重量",{"key":19,"text":20,"correct":21},"C","块体重量",false,{"key":23,"text":24,"correct":14},"D","坡度",{"key":26,"text":27,"correct":14},"E","表面平整度","ABDE","2020版教材页码P144-P147 安放人工块体前，应检查块石垫层厚度、块石重量、坡度和表面平整度，不符合要求时，应进行修整。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]