[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130424":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130424,794,2,"多选题","斜坡堤堤心石抛填，当采用陆上推进法时，堤根的浅水区可一次抛填到顶，堤身和堤头视（ ）影响程度可一次或多次抛填到顶。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","流速",false,{"key":16,"text":17,"correct":14},"B","风速",{"key":19,"text":20,"correct":21},"C","水深",true,{"key":23,"text":24,"correct":21},"D","地基土的强度",{"key":26,"text":27,"correct":21},"E","波浪","CDE","2020版教材页码P143-P144 当采用陆上推进法抛填堤心石时，堤根的浅水区可一次抛填到顶，堤身和堤头视水深、地基土的强度和波浪影响程度可一次或多次抛填到顶。施工机具可视堤顶宽度和工程量大小选用拖拉机、自卸汽车及自卸汽车配装载机等。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]