[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130417":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130417,794,2,"多选题","码头施工区挖泥应按下列要求进行：（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","挖泥前，测量挖泥区水深断面",true,{"key":16,"text":17,"correct":14},"B","按设计或施工要求进行阶梯形分层开挖",{"key":19,"text":20,"correct":21},"C","按设计或施工要求进行逐层开挖",false,{"key":23,"text":24,"correct":14},"D","挖泥完毕后，复测开挖范围的水深断面是否符合要求",{"key":26,"text":27,"correct":21},"E","挖泥施工中，勤测挖泥区水深断面","ABD","2020版教材页码P134-P137 码头施工区挖泥应按下列要求进行: 1. 挖泥前，测量挖泥区水深断面。 2. 应按设计或施工的开挖要求进行阶梯形分层挖泥。 3. 挖泥完毕后，复测开挖范围的水深断面是否符合要求。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]