[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130407":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130407,794,2,"多选题","重力式码头的墙体结构形式有混凝土及钢筋混凝土方块、沉箱、扶壁和大直径圆筒等，其一般施工程序包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","基床清淤",false,{"key":16,"text":17,"correct":18},"B","墙体预制",true,{"key":20,"text":21,"correct":18},"C","墙体预制件出运",{"key":23,"text":24,"correct":18},"D","墙体预制件安装",{"key":26,"text":27,"correct":14},"E","墙体预制件吊安","BCD","2020版教材页码P118-P122 重力式码头的墙体结构形式有混凝土及钢筋混凝土方块、沉箱、扶壁和大直径圆筒等，其一般施工程序包括:墙体构件预制、出运和安装。大型预制件吊运采用的吊具应经设计，并满足强度、刚度和稳定性要求。吊具对薄壁构件不宜产生水平挤压力;整体吊运的合力应与其荷载的重心共线。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]