[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130405":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130405,794,2,"多选题","重力式码头基槽挖泥时要（ ），以保证基槽平面位置准确防止欠挖和超挖。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","勤对标",true,{"key":16,"text":17,"correct":14},"B","勤测水深",{"key":19,"text":20,"correct":21},"C","复测断面",false,{"key":23,"text":24,"correct":21},"D","核对土质",{"key":26,"text":27,"correct":21},"E","复测密度","AB","2020版教材页码P114-P118 挖泥时，要勤对标，勤测水深，以保证基槽平面位置准确，防止欠挖，控制超挖。挖至设计标高时，要核对土质。对有标高和土质\"双控\"要求的基槽，如土质与设计要求不符，应继续下挖，直至相应土层出现为止。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]