[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130404":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130404,794,2,"多选题","当采用排淤法处理软土地基时，对施工期置换淤泥质软基的平面位置及深度检查可选用的方法有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","体积平衡法",true,{"key":16,"text":17,"correct":18},"B","核子密度仪法",false,{"key":20,"text":21,"correct":14},"C","钻孔探摸法",{"key":23,"text":24,"correct":18},"D","标准贯入法",{"key":26,"text":27,"correct":14},"E","探地雷达法","ACE","2020版教材页码P143-P144 置换淤泥质软基的平面位置及深度均应进行施工期和竣工期检查。可选用以下检查方法。当采用其他方法时需进行论证。 1）体积平衡法适用于具备抛填计量条件，抛填石料流失量较小的工程。 2）钻孔探摸法适用于一般工程。 3）探地雷达法适用于一般工程，适用于检查工作量大的工程。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]