[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130402":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130402,794,2,"多选题","板桩码头中的锚碇叉桩由一对叉桩和其上端现浇桩帽组成，叉桩靠（）来承受拉杆的拉力。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","桩在土中的弹性嵌固作用",false,{"key":16,"text":17,"correct":14},"B","桩前面的土体抗力",{"key":19,"text":20,"correct":21},"C","前压斜桩轴向力的水平分力",true,{"key":23,"text":24,"correct":21},"D","后拉斜桩轴向力的水平分力",{"key":26,"text":27,"correct":21},"E","前后斜桩水平分力之和","CDE","2020版教材页码P139-P141 锚碇叉桩是由一对叉桩和其上端现浇桩帽组成。叉桩中前面一根是压桩，后面一根为拉桩。它是靠两根斜桩轴向力的水平分力之和来承受拉杆的拉力。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]