[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130369":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130369,794,2,"多选题","工程施工进度计划的实施包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","总进度计划目标的分解",true,{"key":16,"text":17,"correct":18},"B","绘制施工进度计划图",false,{"key":20,"text":21,"correct":14},"C","组织资源供应",{"key":23,"text":24,"correct":14},"D","落实承包责任制",{"key":26,"text":27,"correct":14},"E","落实施工条件","ACDE","工程施工进度计划的实施重点有以下几方面:（一）总进度计划的目标分解； （二）落实施工条件； （三）组织资源供应； （四）落实承包责任制，充分调动各方面的积极性。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]