[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130325":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130325,794,2,"多选题","高桩码头工程施工组织设计编制中，“各项资源的需用计划”包括：劳动力需用计划、材料需用计划、（ ）等。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工资计划",false,{"key":16,"text":17,"correct":18},"B","预制构件和半成品需用计划",true,{"key":20,"text":21,"correct":18},"C","施工船舶和机械需用计划",{"key":23,"text":24,"correct":14},"D","分期分批竣工项目计划",{"key":26,"text":27,"correct":14},"E","混凝土试验计划","BC","各项资源的需用计划主要包括:劳动力、材料、施工船舶和机械、预制构件和半成品需用计划。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]