[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130285":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130285,794,2,"多选题","施工作业者提出水上水下施工作业申请时，提供的申请资料包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","有关管理部门对该项目批准的文件",true,{"key":16,"text":17,"correct":18},"B","项目的施工组织设计",false,{"key":20,"text":21,"correct":18},"C","工地文明施工计划及措施",{"key":23,"text":24,"correct":14},"D","施工作业者的资质认证文件",{"key":26,"text":27,"correct":14},"E","法人资格证明文件","ADE","",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]