[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130222":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130222,794,2,"多选题","堆载预压工程应作好施工监测和效果检验，工程结束后应进行（ ），必要时尚应进行现场载荷试验。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","动力触探试验",false,{"key":16,"text":17,"correct":18},"B","室内土工试验",true,{"key":20,"text":21,"correct":18},"C","十字板剪切试验",{"key":23,"text":24,"correct":14},"D","标准贯入试验",{"key":26,"text":27,"correct":18},"E","静力触探","BCE","",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]