[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130187":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130187,794,2,"多选题","堆载预压施工时，应根据设计要求分级加载，通过观测（ ）来控制加载速率。在打设排水体之前，应测出原地基表面的高程，作为控制依据。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","加土量",false,{"key":16,"text":17,"correct":14},"B","加荷速率",{"key":19,"text":20,"correct":14},"C","土体变形",{"key":22,"text":23,"correct":24},"D","垂直位移",true,{"key":26,"text":27,"correct":24},"E","水平位移","DE","",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]