[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130153":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130153,794,2,"多选题","工程勘察报告《附图和附表》中应包括：综合工程地质图，原位测试图表，土工试验图表，（ ）等内容。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程勘察施工日记表",false,{"key":16,"text":17,"correct":18},"B","勘察点平面位置图",true,{"key":20,"text":21,"correct":18},"C","工程地质剖面图",{"key":23,"text":24,"correct":18},"D","钻孔柱状图",{"key":26,"text":27,"correct":18},"E","各岩土单元体的物理、力学指标统计表","BCDE","",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]