[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130129":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130129,794,2,"多选题","对于冬期施工利弊，说法正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","不利于混凝土强度增长",true,{"key":16,"text":17,"correct":18},"B","不利于大体积混凝土入模温度控制",false,{"key":20,"text":21,"correct":18},"C","有利于模板周转",{"key":23,"text":24,"correct":14},"D","有利于降低大体积混凝土温度",{"key":26,"text":27,"correct":18},"E","一定会加大施工成本","AD","冬季过低的温度会使钢筋焊接头发生冷脆，还会减慢混凝土强度的增长速度，延长拆模时间，减慢模板的周转，有时还会大幅增加混凝土的加温和保温措施费用。冬季低温冰冻会增加火灾等安全隐患。低温对混凝土的质量事故有隐蔽和滞后的作用。冬期施工的混凝土工程缺陷多数在之后的春夏季才开始暴露出来，这种暴露问题的滞后性还会给事故的调查处理带来难度。 气温剧烈变化（冷击）还会导致大体积混凝土的内表温差加大，过大的温差会使大体积混凝土产生裂缝。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]