[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130112":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130112,794,2,"多选题","板桩码头建筑物沉桩施工时，当土层变化较大，且需要分区确定桩长时，对于钢筋混凝土板桩长度的确定应秉承（ ）原则。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","宜短勿长",false,{"key":16,"text":17,"correct":18},"B","宜长勿短",true,{"key":20,"text":21,"correct":14},"C","按设计要求确定合适桩长",{"key":23,"text":24,"correct":18},"D","宁可截桩，不要接桩",{"key":26,"text":27,"correct":14},"E","宁可接桩，不要截桩","BD","当土层变化较大，且需分区确定桩长时，为避免在现场接桩，影响施工进度，钢筋混凝土板桩\"宜长勿短即宁可截桩，不要接桩。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]