[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130108":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130108,794,2,"多选题","板桩码头建筑物施工沉桩前，（ ）均应按勘测基线（点）及水准点测设，其精度符合有关规定，并应定期检查和校核。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工基线",true,{"key":16,"text":17,"correct":14},"B","桩位控制点",{"key":19,"text":20,"correct":21},"C","平面控制网",false,{"key":23,"text":24,"correct":14},"D","现场水准点",{"key":26,"text":27,"correct":21},"E","高程控制网","ABD","",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]