[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130083":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130083,794,2,"多选题","基床夯实后，应进行夯实检验。检验时，每个夯实施工段（按土质和基床厚度划分）抽查不少于5m一段基床，用（ ）复打一夯次（夯锤相邻排列，不压半夯）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","原夯锤",true,{"key":16,"text":17,"correct":14},"B","原夯击能",{"key":19,"text":20,"correct":21},"C","原锤重",false,{"key":23,"text":24,"correct":21},"D","原锤型",{"key":26,"text":27,"correct":21},"E","设计夯锤","AB","",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]