[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130078":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130078,794,2,"多选题","在计算耙吸挖泥船施工时间利用率时，其挖泥时间是指（ ）等时间。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","挖泥",true,{"key":16,"text":17,"correct":14},"B","运泥",{"key":19,"text":20,"correct":14},"C","抛泥",{"key":22,"text":23,"correct":14},"D","吹泥",{"key":25,"text":26,"correct":27},"E","吹水",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]