[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130073":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130073,794,2,"多选题","换填地基应通过试验和试验性施工确定的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工方法",true,{"key":16,"text":17,"correct":18},"B","施工定额",false,{"key":20,"text":21,"correct":14},"C","最优含水率",{"key":23,"text":24,"correct":14},"D","分层厚度",{"key":26,"text":27,"correct":14},"E","每层的压实遍数","ACDE","",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]