[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130053":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130053,794,2,"多选题","板桩建筑物锚碇系统拉杆安装时，在满足条件（ ）后，方可张紧拉杆。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","锚碇结构前回填完成",true,{"key":16,"text":17,"correct":18},"B","锚碇结构后回填完成",false,{"key":20,"text":21,"correct":14},"C","锚碇结构的现浇混凝土达到设计强度",{"key":23,"text":24,"correct":14},"D","板桩墙导梁或胸墙的现浇混凝土达到设计强度",{"key":26,"text":27,"correct":18},"E","拉杆防护层检查完好","ACD","",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]