[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130037":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130037,794,2,"多选题","重力式码头沉箱采用浮运拖带法时，拖带前应进行以下项目的验算：（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","总体强度",false,{"key":16,"text":17,"correct":18},"B","吃水",true,{"key":20,"text":21,"correct":14},"C","局部承载力",{"key":23,"text":24,"correct":18},"D","压载",{"key":26,"text":27,"correct":18},"E","浮运稳定","BDE","",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]