[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130026":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1130026,794,2,"多选题","回填土吹填施工时，排水口宜远离码头前沿，其口径尺寸和高程应根据（ ）确定。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","回淤隋况",false,{"key":16,"text":17,"correct":18},"B","排水要求",true,{"key":20,"text":21,"correct":18},"C","沉淀效果",{"key":23,"text":24,"correct":14},"D","施工水位",{"key":26,"text":27,"correct":14},"E","排水效果","BC","排水口宜远离码头前沿，其口径尺寸和高程应根据排水要求和沉淀效果确定。",{"id":6,"name":31,"category":32,"favorite":33},"一建港口与航道工程实务","建筑工程",0]