[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1130007":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1130007,794,1,"单选题","《内河航运水工建筑工程定额》是以（ ）为单位并用人工、材料和船舶机械艘（台）班消耗量表示的工程定额,是计算内河航运水工建筑工程定额直接费的依据。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分部工程",false,{"key":16,"text":17,"correct":18},"B","分项工程",true,{"key":20,"text":21,"correct":14},"C","单位工程",{"key":23,"text":24,"correct":14},"D","检验批","2020版教材页码P359-P360 《内河航运水工建筑工程定额》JTS\u002FT 275- 1-2019 是以分项工程为单位并用人工、材料和船舶机械艘（台）班消耗量表示的工程定额，是计算内河航运水工建筑工程定额直接费的依据;本定额应与《水运建设工程概算预算编制规定》 JTST 116- 2019、 《内河航运 工程船舶机械艘（台）班费用定额》JTS\u002FT 275- 2- 2019和《水运工程混凝土及砂浆材料用量定额》JTS\u002FT 277- 2019配套使用。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]