[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129975":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1129975,794,1,"单选题","分期实施的疏浚工程按（ ）划分单位工程。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程量",false,{"key":16,"text":17,"correct":14},"B","疏浚土质情况",{"key":19,"text":20,"correct":21},"C","施工阶段",true,{"key":23,"text":24,"correct":14},"D","工期长短","2020版教材页码P323-P327 分期实施的疏浚工程按施工阶段划分单位工程。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]