[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129960":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1129960,794,1,"单选题","项目进度控制应以实现（ ）为最终目标。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","最短工期",false,{"key":16,"text":17,"correct":14},"B","最大经济效益",{"key":19,"text":20,"correct":21},"C","施工合同约定的竣工日期",true,{"key":23,"text":24,"correct":14},"D","业主下达的工期","2020版教材页码P317-P319 项目进度控制应依实现施工合同约定的竣工日期为最终目标。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]