[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129959":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1129959,794,1,"单选题","在对进度计划调整时，对落后的关键线路（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","无需调整",false,{"key":16,"text":17,"correct":18},"B","必须采取措施加快",true,{"key":20,"text":21,"correct":14},"C","允许暂时落后",{"key":23,"text":24,"correct":14},"D","利用以后的时差可自然调整","2020版教材页码P321-P323 对落后的关键线路，落后过多（已超过前方可利用时差）的非关键线路，现时虽落后不多，但可预见未来会落后更多、将妨碍关键线路进展（那时，它将成为新的关键线路）的非关键线路，必须采取措施使之加快。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]