[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129958":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1129958,794,1,"单选题","工程月、旬（或周）施工进度计划是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实施性的作业计划",true,{"key":16,"text":17,"correct":18},"B","控制性计划",false,{"key":20,"text":21,"correct":18},"C","确定总进度目标的计划",{"key":23,"text":24,"correct":18},"D","控制总工期的计划","2020版教材页码P319-P321 月、旬（或周）施工进度计划是实施性的作业计划，应在月、旬（或周）末，由项目经理部提出，经工地例会协调后编制。月、旬（或周）施工进度计划应逐级落实，最终通过施工任务书由班组实施。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]