[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129956":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1129956,794,1,"单选题","港口与航道工程施工中，（ ）不是工期索赔计算的分析方法。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","网络分析方法",false,{"key":16,"text":17,"correct":14},"B","按实际记录确定补偿工期",{"key":19,"text":20,"correct":21},"C","概率分析法",true,{"key":23,"text":24,"correct":14},"D","比例分析法","2020版教材页码P315 在计算一个或多个延误引起的工期索赔时，通常可采用如下三种分析方法: 一、网络分析方法； 二、比例类推法 1.按造价进行比例类推 2. 按工程量进行比例类推 三、其他方法：如:按实际工期延长记录确定补偿天数等。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]