[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129953":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1129953,794,1,"单选题","总概算应控制在建设项目工程可行性研究阶段批准的（ ）允许范围内。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投资总估算",true,{"key":16,"text":17,"correct":18},"B","最高限额",false,{"key":20,"text":21,"correct":18},"C","全部费用",{"key":23,"text":24,"correct":18},"D","总投资额","2020版教材页码P305-P309 总概算应控制在建设项目工程可行性研究阶段批准的投资总估算允许范围内。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]