[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129949":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1129949,794,1,"单选题","在对进度计划调整时，大量超前领先的非关键线路（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","应继续保持其领先地位",false,{"key":16,"text":17,"correct":14},"B","对于保证进度计划是有利的",{"key":19,"text":20,"correct":21},"C","可能受其他线路发展的制约，中途不得不临时停工",true,{"key":23,"text":24,"correct":14},"D","可能转化为关键线路","2020版教材页码P292-P293 对过于领先的非关键线路，可能受其他线路发展的制约，中途不得不临时停工，造成窝工浪费，应及早预见，通过进度调整，予以避免。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]