[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129934":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1129934,794,1,"单选题","在沉箱重力式码头施工中，沉箱安放就位填充完毕后，后方抛石棱体及倒滤层的抛填，应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","从墙后开始抛填",true,{"key":16,"text":17,"correct":18},"B","在岸边从陆上向海中推填",false,{"key":20,"text":21,"correct":18},"C","根据施工方便随机抛填",{"key":23,"text":24,"correct":18},"D","海、陆双向对头抛填","2020版教材页码P292-P293 抛石棱体及倒滤层的抛填。抛填顺序应从墙后开始，避免将岸坡淤泥挤入棱体下。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]