[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129923":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1129923,794,1,"单选题","港口与航道工程图纸的熟悉与审查应由（ ）来负责组织。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目总工程师",false,{"key":16,"text":17,"correct":18},"B","项目经理",true,{"key":20,"text":21,"correct":14},"C","设计代表",{"key":23,"text":24,"correct":14},"D","总监理工程师","2020版教材页码P278-P279 图纸的审查，一般分为两种形式。 第一种是综合会审:收到项目的施工图后，由总包单位和分包单位分别对图纸进行审查和熟悉，然后进行综合会审，或在设计交底时与设计单位、建设单位和监理单位一起进行综合会审，以解决大的方案性问题和各专业之间的搭接和协调问题。 第二种是由工程项目经理负责组织各工种对图纸进行学习、熟悉、审查，同时组织各专业间的会审。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]