[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129921":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1129921,794,1,"单选题","港口与航道工程的技术交底应当做到（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","技术交底要填写技术交底记录单",true,{"key":16,"text":17,"correct":18},"B","正式施工前要一次全面交底完毕",false,{"key":20,"text":21,"correct":18},"C","将施工组织设计的主要方案交代清楚",{"key":23,"text":24,"correct":18},"D","项目部技术人员清楚设计意图","2020版教材页码P279-P280 技术交底是一项经常性的工作，要分级、分阶段地进行。项目经理要根据项目施工的进度，分阶段组织向相关人员交底，并督促和检查操作层交底和落实所交底内容的情况。 各层次各项交底，除有口头交底、文字交底材料的记载外，必要时应有图示、图表、实样、现场示范操作等，同时，要填写《技术交底记录单》。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]