[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129912":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1129912,794,1,"单选题","承包人在自检合格后，填写隐蔽工程验收申请单，在覆盖前（ ）通知监理人进行验收。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","8h",false,{"key":16,"text":17,"correct":14},"B","12h",{"key":19,"text":20,"correct":14},"C","24h",{"key":22,"text":23,"correct":24},"D","48h",true,"2020版教材页码P229-P230 承包人在自检合格后，填写隐蔽工程验收申请单，在覆盖前48h ，通知监理人进行验收;监理人在接到通知48h 内进行验收。经监理人验收合格并在验收记录上签认后，承包人可进行覆盖和继续施工;若验收不合格，承包人应按监理人的要求整改并重新申请验收。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]