[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129911":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1129911,794,1,"单选题","承包人应在计划开工日期（ ）前，向发包人和监理人报送施工组织设计。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5d",false,{"key":16,"text":17,"correct":18},"B","7d",true,{"key":20,"text":21,"correct":14},"C","14d",{"key":23,"text":24,"correct":14},"D","28d","2020版教材页码P229 承包人应在计划开工日期7d前，向发包人和监理人报送施工组织设计;监理人应在7d 内批复或提出修改意见，否则视为已得到批准。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]