[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129910":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1129910,794,1,"单选题","承包人对所施工工程的照管和维护责任到（ ）为止。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","隐蔽工程验收合格",false,{"key":16,"text":17,"correct":14},"B","主体工程验收合格",{"key":19,"text":20,"correct":21},"C","工程接收证书颁发",true,{"key":23,"text":24,"correct":14},"D","工程交工并结算","2020版教材页码P224-P229 工程接收证书颁发前，承包人应负责照管和维护工程。工程接收证书颁发时尚有部分未竣工工程的，承包人还应负责该未竣工工程的照管和维护工作，直至竣工后移交给发包人为止。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]