[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129904":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1129904,794,1,"单选题","调整工程量清单项目的综合单价的前提，是依据该单项工程量的变化幅度和对合同总价影响幅度确定。当变化幅度达（ ）时可调整。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","单项超10％且总价超2％",false,{"key":16,"text":17,"correct":14},"B","单项超10％且总价超3％",{"key":19,"text":20,"correct":21},"C","单项超20％且总价超2％",true,{"key":23,"text":24,"correct":14},"D","单项超20％且总价超3％","2020版教材页码P232-P233 工程量清单中某单项工程量的变化幅度超过20%。且对合同总价影响幅度超过2%时，应调整该工程量清单项目的综合单价。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]