[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129903":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1129903,794,1,"单选题","分项工程的开工应事先得到监理人的书面同意，承包人应提前（ ）将申请开工的书面通知报送监理人。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","8h",false,{"key":16,"text":17,"correct":14},"B","12h",{"key":19,"text":20,"correct":14},"C","24h",{"key":22,"text":23,"correct":24},"D","48h",true,"2020版教材页码P229 分项工程的开工应事先得到监理人的书面同意，承包人应提前48h将申请开工的书面通知报送监理人，监理人应在收到通知48h 内予以书面答复，否则视为同意。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]