[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129902":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1129902,794,1,"单选题","发包人向承包人提供施工现场地质、地下管线、测量控制点交验等资料的时间，是在计划开工日期（ ）前。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7d",false,{"key":16,"text":17,"correct":14},"B","10d",{"key":19,"text":20,"correct":21},"C","14d",true,{"key":23,"text":24,"correct":14},"D","21d","2020版教材页码P224-P229 发包人应在计划开工日期14d前向承包人提供与施工现场相关的工程地质和地下管线资料，工程地质报告以及交验测量的水准点、坐标控制点等技术资料，并对其提供的上述资料的真实性、准确性负责。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]