[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129896":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1129896,794,1,"单选题","港口与航道工程施工合同，（ ）单位应该按合同条款约定的数量向施工单位提供工程地质报告以及水准点等技术资料。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计单位",false,{"key":16,"text":17,"correct":14},"B","监理单位",{"key":19,"text":20,"correct":21},"C","建设单位",true,{"key":23,"text":24,"correct":14},"D","招标单位","2020版教材页码P224-P229 发包人应在计划开工日期14d前向承包人提供与施工现场相关的工程地质和地下管线资料，工程地质报告以及交验测量的水准点、坐标控制点等技术资料，并对其提供的上述资料的真实性、准确性负责。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]