[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129891":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1129891,794,1,"单选题","水运工程招标人自招标文件开始发售之日起至潜在投标人提交投标文件截止之日止最短不得少于（ ）日。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","20",true,{"key":16,"text":17,"correct":18},"B","30",false,{"key":20,"text":21,"correct":18},"C","35",{"key":23,"text":24,"correct":18},"D","40","2020版教材页码P214-P218 自招标文件开始发售之日起至潜在技标人提交投标文件截止之日止，最短不得少于20 日。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]