[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129883":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1129883,794,1,"单选题","（ ），有船单位和项目经理部要编制防台预案。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","每年进入台风季节后",false,{"key":16,"text":17,"correct":18},"B","每年台风季节到来前",true,{"key":20,"text":21,"correct":14},"C","每年年初",{"key":23,"text":24,"correct":14},"D","任何时候","2020版教材页码P264-P268 每年台风季节到来前，有船单位和项目经理部要编制防台预案。工程船舶要落实项目部制定的各项安全技术措施，并根据现场情况选择安排可靠的船舶避风锚地和停靠地点，制定船舶防台安全技术措施，绘制工程船舶锚泊图。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]