[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129870":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1129870,794,1,"单选题","编队（组）航行时，（ ）负责主持制定拖航计划和安全实施方案。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","被拖船船长",false,{"key":16,"text":17,"correct":14},"B","任一拖船船长",{"key":19,"text":20,"correct":14},"C","助拖船船长",{"key":22,"text":23,"correct":24},"D","主拖船船长",true,"2020版教材页码P261-P264 对单船或两艘拖轮及其两艘以上执行同一任务，均应指定主拖船长担任总指挥，负责拖航全程的管理指挥。总指挥对全程拖航安全负责，包括被拖航船的拖航安全，对整个船队的航行有绝对指挥权。 由总指挥负责主持制订拖航计划和安全实施方案。拖航计划和实施方案应包括任务、区域、日期、气象、方法、通信联络方式、应急安全措施等。拖航计划和安全实施方案制定后须经企业负责人签认，报请海事主管部门检验审核批准，并办理拖航许可证书。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]