[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129852":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1129852,794,1,"单选题","对于变更的估价，工程量清单中无适用或类似子目的单价，可按照（ ）的原则，由监理人按合同约定商定或确定变更工作的单价。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","成本",false,{"key":16,"text":17,"correct":14},"B","成本加利润减管理费",{"key":19,"text":20,"correct":21},"C","成本加利润",true,{"key":23,"text":24,"correct":14},"D","成本加利润加管理费","2020版教材页码P238 变更的估价原则： 1.己标价工程量清单中有适用于变更工作的子目的，采用该子目的单价。 2.巳标价工程量清单中无适用于变更工作的子目，但有类似子目的，可在合理范围内参照类似子目的单价，由监理人按合同约定商定或确定变更工作的单价。 3. 己标价工程量清单中无适用或类似子目的单价，可按照成本加利润的原则，由监理人按合同约定商定或确定变更工作的单价。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]