[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1129850":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1129850,794,1,"单选题","工程量清单计价采用（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","市场价格单价",false,{"key":16,"text":17,"correct":14},"B","定额价格单价",{"key":19,"text":20,"correct":14},"C","协商价格单价",{"key":22,"text":23,"correct":24},"D","综合单价",true,"2020版教材页码P233-P235 工程量清单计价采用综合单价计价方式。",{"id":6,"name":27,"category":28,"favorite":29},"一建港口与航道工程实务","建筑工程",0]